By: Our Staff Reporter
Addis Ababa (Ethiopia Today), July 21, 2026: The civil engineering team at the Koisha Hydropower Project has completed the first phase of structural concrete placement for its powerhouse, marking a major milestone for Ethiopia’s third-largest electricity generation project, state power utility Ethiopian Electric Power (EEP) announced.
Project Civil Engineer Yitagesu Ayalew stated that Koisha ranks as the country’s third-largest hydropower development, positioned directly behind the flagship Grand Ethiopian Renaissance Dam (GERD) and the Gibe III Hydropower Project.

To clear the site before constructing the dam’s main roller-compacted concrete (RCC) structure, engineering crews successfully excavated more than 7 million cubic meters of overburden and loose soil.
Progress continues at a steady pace on the main dam structure itself, with over 6.2 million cubic meters of roller-compacted concrete already placed out of the planned 7.725 million cubic meters.
Construction crews are operating around the clock in two continuous shifts to accelerate civil works, placing an average of over 100,000 cubic meters of roller-compacted concrete every month.
Upon completion, the Koisha Hydropower Project will serve as a key energy asset for Ethiopia, playing a central role in expanding the country’s national electricity generation capacity and regional grid integration.