By: Our Staff Reporter
Ethiopia Today (Addis Ababa), November 20, 2026: The Civil Bench of Ethiopia’s Federal High Court has ordered the auction of apartments owned by Flintstones Engineering Share Company in Addis Ababa’s Bole Sub-City (Woreda 10) to settle outstanding debts owed to 87 homebuyers.
Issued during a hearing on November 19, 2026, the execution order enforces an arbitration ruling originally passed on June 8, 2024, following a legal battle lasting over three years.
According to court documents and a verification report by the Federal Courts Execution Directorate, the properties registered under the company’s name on plot number 10/69/1/6/43191/00 will be sold starting with units that are at least 80 percent complete, expanding to less-finished units if needed to cover the debt, with any surplus funds returning to the company.
The dispute arose after Flintstones failed to deliver the homes within the agreed two-and-a-half-year contract period; while buyers initially demanded compensation at the prevailing market rate of 99,000 Birr per square meter, the arbitration tribunal was later upheld by the Federal Supreme Court Cassation Bench, which ruled in favor of a 24,000 Birr per square meter payout, culminating in this week’s enforcement order.